Okemos Bathroom Remodel

Project Overview

The existing bathroom in this Okemos home was functional but in need of a refresh. The homeowner in particular didn't like the basin/shower. This remodel included removing a portion of wall to open up the shower, which meant moving the plumbing supply. The vanity was updated with a chase in the wall to the right, and we brought the bathroom heat supply up to code and updated the flooring, electrical, and lighting. The bathroom was essentially gutted to the studs and updated throughout, with Pioneer Cabinetry for more usable storage and an Onyx Collection cultured stone base and surround in the shower.

Project Foreman

Phill Nanasy

Project Designer

Jaime Dunn

Project Goals

  • Replace cabinetry with Pioneer Cabinetry to make more useful storage.
  • Update shower using Onyx Collection cultured stone base and surround.
  • Update bathroom flooring.
  • Brighten the space.

Project Cost Category

Bathroom Midrange Economy

Project Development Start

MAY 12, 2023

Production
Start

SEPTEMBER 5, 2023

Project
Completion

DECEMBER 1, 2023